Cordial Leora Work Status

Explore the work status of Cordial Leora, Super luxury Apartments in Trivandrum

Book a site visit
Work Status as of June 2026
Sl. No Work Description Status
1Retaining wall worksCompleted
2Piling workCompleted
3Foundation incl. pile cap, grade beam & grade slabCompleted
4Column Work
Lower Ground 2 to Lower Ground 1Completed
Lower Ground 1 to Ground FloorCompleted
Ground Floor to First FloorCompleted
First Floor to Second FloorCompleted
Second Floor to Third FloorCompleted
Third Floor to 4th FloorCompleted
4th Floor to 5th FloorCompleted
5th Floor to 6th FloorCompleted
6th Floor to 7th Floor50% Completed
5Sump tankCompleted
6Lift pit workCompleted
7Ramp Concrete
Lower Ground 2 to Lower Ground 1Completed
Lower Ground 1 to Ground FloorCompleted
8Slab Work
Lower Ground 1 floor slabCompleted
Ground floor slabCompleted
First floor slabCompleted
Second floor slabCompleted
Third floor slabCompleted
4th floor slabCompleted
5th floor slabCompleted
6th floor slabCompleted
9Ceiling Plastering
First floorCompleted
Second floorCompleted
Third floorCompleted
10Block Work
First floorCompleted
Second floorIn Progress
Third floorIn Progress
Work Status as of May, 2026
Sl. No. Work Description Status
1 Retaining Wall Works Completed
2 Piling Work Completed
3 Foundation Including Pile Cap, Grade Beam & Grade Slab Work Completed
4 Column Work
4.1 Lower Ground 2 to Lower Ground 1 Completed
4.2 Lower Ground 1 to Ground Floor Completed
4.3 Ground Floor to First Floor Completed
4.4 First Floor to Second Floor Completed
4.5 Second Floor to Third Floor Completed
4.6 Third Floor to Fourth Floor Completed
4.7 Fourth Floor to Fifth Floor Completed
4.8 Fifth Floor to Sixth Floor 70% Completed
5 Sump Tank Completed
6 Lift Pit Work Completed
7 Ramp Concrete
7.1 Lower Ground 2 to Lower Ground 1 Completed
7.2 Lower Ground 1 to Ground Floor Completed
8 Slab Work
8.1Lower Ground 1 Floor SlabCompleted
8.2Ground Floor SlabCompleted
8.3First Floor SlabCompleted
8.4Second Floor SlabCompleted
8.5Third Floor SlabCompleted
8.6Fourth Floor SlabCompleted
8.7Fifth Floor SlabCompleted
9 Ceiling Plastering
9.1First FloorCompleted
9.2Second Floor25% Completed
10 Block Work
10.1First Floor50% Completed
Work Status as of April, 2026

1

Retaining wall works

Completed

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

 

First floor to Second floor

Completed

 

Second floor to third floor

Completed

 

Third floor to 4th floor

Completed

 

4th floor to 5th floor

Completed

 

5th floor to 6th floor

In Progress

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

Completed

 

Second floor slab

Completed

 

Third floor slab

Completed

 

4th Floor slab

Completed

 

5th Floor slab

75% Completed

9

Ceiling Plastering

 

 

First floor

In Progress

Work Status as of March, 2026

Sl.No

Work Description

Status as on Mar.30, 2026

1

Retaining wall works

Completed

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

 

First floor to Second floor

Completed

 

Second floor to third floor

Completed

 

Third floor to 4th floor

Completed

 

4th floor to 5th floor

In Progress

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

Completed

 

Second floor slab

Completed

 

Third floor slab

Completed

 

4th Floor slab

Completed

 

5th Floor slab

In Progress

9

Ceiling Plastering

 

 

First floor

In Progress

Work Status as of February, 2026

1

Retaining wall works

Completed

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

 

First floor to Second floor

Completed

 

Second floor to third floor

Completed

 

Third floor to 4th floor

In Progress

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

Completed

 

Second floor slab

Completed

 

Third floor slab

Completed

 

4th Floor slab

In Progress

Work Status as of January, 2026

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

 

First floor to Second floor

Completed

 

Second floor to third floor

In Progress

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

Completed

 

Second floor slab

Completed

 

Third floor slab

In Progress

Work Status as of Dec 31, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

 

First floor to Second floor

In Progress

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

Completed

 

Second floor slab

In Progress

Work Status as of Nov.30, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

 

Ground floor to First floor

Completed

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

Completed

8

slab work

 

 

Lower ground 1 floor slab

Completed

 

Ground floor slab

Completed

 

First floor slab

In Progress

Work Status as of Oct.30, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

100% Completed

 

Ground floor to First floor

40% Completed

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

In progress

8

slab work

 

 

Lower ground 1 floor slab

100% Completed

 

Ground floor slab

75% Completed

Work Status as of Oct. 05, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Foundation including Pile cap, Grade beam and Grade slab work

 Completed

4

Column work

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

90% Completed

5

Sump tank

Completed

6

Lift pit work

Completed

7

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

In progress

8

slab work

 

 

Lower ground 1 floor slab

90% Completed

 

Ground floor slab

In progress

Work Status as of August 31, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Pile cap work

98% Completed

4

Grade beam work

90% Completed

5

Grade slab work

80% Completed

6

Column work

 

 

Lower ground 2 to Lower ground 1

90% Completed

 

Lower ground 1 to Ground floor

50% Completed

7

Sump tank

Completed

8

Lift pit work

Completed

9

Ramp concrete

 

 

Lower ground 2 to Lower ground 1

Completed

 

Lower ground 1 to Ground floor

In progress

10

slab work

 

 

Lower ground 1 floor

80% Completed

 

Ground floor slab

In progress

Work Status as of July 31, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Pile cap work

85% Completed

4

Grade beam work

75% Completed

5

Grade slab work

70% Completed

6

Lower ground 2 to Lower ground 1 Column work

75% Completed

6

Sump tank

Completed

8

Lift pit work

Completed

9

Ramp concrete (Lower ground 2 to Lower ground 1)

Completed

10

Lower ground 1 floor slab work

50% Completed

Work Status as of June 30, 2025

1

Retaining wall works

In Progress

2

Piling work

Completed

3

Pile cap work

80% Completed

4

Grade beam work

70% Completed

5

Grade slab work

50% Completed

6

Sump tank

Completed

7

Lift pit work

Completed

8

Ramp concrete (Lower ground 2 to Lower ground 1)

80% Completed

9

Lower ground 1 slab work

In progress

Work Status as of June, 2025
Retaining wall worksIn Progress
Piling workCompleted
Pile cap work60% Completed
Grade beam work50% Completed
Grade slab work30% Completed
Sump tankCompleted
Lift pit workCompleted
Work Status as of April 29, 2025
  • Retaining wall works : In progress
  • Piling work: Completed
  • Pie Cap work: 40% Completed
  • Grade Beam Work: 10% Completed
  • Sump Tank: 80% Completed
  • Lift Pit Work: 40% Completed
Work Status as of April 12, 2025
  • Piling completed in quick time of under 90 days along with successful Static load test on working pile.
  • Retaining wall completed for boundary.
  • Pile cap started with sump tank.
Work Status as of March 31, 2025
  • Retaining wall works : In Progress
  • Piling work: 75% Completed
  • Pile Cap Work: Started
March 2025
𝐒𝐭𝐚𝐭𝐢𝐜 𝐏𝐢𝐥𝐞 𝐋𝐨𝐚𝐝 𝐓𝐞𝐬𝐭 𝐒𝐮𝐜𝐜𝐞𝐬𝐬𝐟𝐮𝐥𝐥𝐲 𝐂𝐨𝐧𝐝𝐮𝐜𝐭𝐞𝐝 𝐚𝐭 𝐂𝐨𝐫𝐝𝐢𝐚𝐥 𝐋𝐞𝐨𝐫𝐚!
Ensuring strength, stability, and durability! The Static Pile Load Test has been successfully conducted at Cordial Leora, our newly launched super luxury apartment project at Kuravankonam, Trivandrum. This crucial test guarantees that the foundation meets the highest structural standards, reinforcing our commitment to excellence in construction.

Work status- Cordial Leora