Construction Progress

Cordial Leora Construction Status: Work Progress Updates

Regular Cordial Leora work progress updates with photographs, as per RERA compliance requirements. All updates are dated and verified.

RERA Registration
K-RERA/PRJ/TVM/215/2024
Verify at rera.kerala.gov.in ↗
Project Type
Lower Ground 1 and 2 + Ground + 15 floors
54 apartments, 2, 3 & 4 BHK
Location
Kuravankonam, Kowdiar
Trivandrum, Kerala
Last Updated
September 2026
Monthly updates
Works status as of September 2026
Sl.No Work description Status
1 Retaining wall works Completed
2 Piling work Completed
3 Foundation including Pile cap, Grade beam and Grade slab work Completed
4 #Column work In Progress
5 Lower ground 2 to Lower ground 1 Completed
6 Lower ground 1 to Ground floo Completed
7 Ground floor to First floor Completed
8 First floor to Second floor Completed
9 Second floor to third floor Completed
10 Third floor to 4th floor Completed
11 4th floor to 5th floor Completed
12 5th floor to 6th floor Completed
13 6th floor to 7th floor Completed
14 7th floor to 8th floor Completed
15 8th floor to 9th floor Completed
16 9th floor to 10th floor Completed
17 Sump tank Completed
18 Lift pit work Completed
19 #Ramp concrete In Progress
20 Lower ground 2 to Lower ground 1 Completed
21 Lower ground 1 to Ground floor Completed
22 #slab work In Progress
23 Lower ground 1 floor slab Completed
24 Ground floor slab Completed
25 First floor slab Completed
26 Second floor slab Completed
27 Third floor slab Completed
28 4th Floor slab Completed
29 5th Floor slab Completed
30 6th Floor slab Completed
31 7th Floor slab Completed
32 8th Floor slab Completed
33 9th Floor slab Completed
34 10th Floor slab In Progress
35 #Ceiling Plastering In Progress
36 First floor Completed
37 Second floor Completed
38 Third floor Completed
39 4th Floor Completed
40 5th Floor Completed
41 6th Floor In Progress
42 #Block work In Progress
43 First floor Completed
44 Second floor Completed
45 Third floor Completed
46 4th Floor (70% completed) In Progress
47 #Inside Plastering In Progress
48 First floor Completed
49 Second floor In Progress
50 Third floor In Progress
51 #Electrical work In Progress
52 1st floor Wall chasing and box fixing Completed
53 2nd floor Wall chasing and box fixing(70% Completed) In Progress
54 3rd floor Wall chasing and box fixing Completed
Works status as of August 2026
Sl.No Work description Status
1 Retaining wall works Completed
2 Piling work Completed
3 Foundation including Pile cap, Grade beam and Grade slab work Completed
4 # Column work In Progress
5 - Lower ground 2 to Lower ground 1 Completed
6 - Lower ground 1 to Ground floor Completed
7 - Ground floor to First floor Completed
8 - First floor to Second floor Completed
9 - Second floor to Third floor Completed
10 - Third floor to 4th floor Completed
11 - 4th floor to 5th floor Completed
12 - 5th floor to 6th floor Completed
13 - 6th floor to 7th floor Completed
14 - 7th floor to 8th floor Completed
15 - 8th floor to 9th floor (80% Completed) In Progress
16 Sump tank Completed
17 Lift pit work Completed
18 # Ramp concrete In Progress
19 - Lower ground 2 to Lower ground 1 Completed
20 - Lower ground 1 to Ground floor Completed
21 # Slab work In Progress
22 - Lower ground 1 floor slab Completed
23 - Ground floor slab Completed
24 - First floor slab Completed
25 - Second floor slab Completed
26 - Third floor slab Completed
27 - 4th Floor slab Completed
28 - 5th Floor slab Completed
29 - 6th Floor slab Completed
30 - 7th Floor slab Completed
31 - 8th Floor slab Completed
32 - 9th Floor slab In Progress
33 # Ceiling Plastering In Progress
34 - First floor Completed
35 - Second floor Completed
36 - Third floor Completed
37 - 4th Floor Completed
38 - 5th Floor In Progress
39 # Block work In Progress
40 - First floor Completed
41 - Second floor Completed
42 - Third floor Completed
43 - 4th Floor In Progress
44 # Inside Plastering In Progress
45 - 1st floor (90% completed In Progress
46 # Electrical work In Progress
47 - 1st floor Wall chasing and box fixing Completed
48 - 2nd floor Wall chasing and box fixing In Progress
49 - 3rd floor Wall chasing and box fixing In Progress
Status as on July 31, 2026
Sl.No Work description Status
1 Retaining wall works Completed
2 Piling work Completed
3 Foundation including Pile cap, Grade beam and Grade slab work Completed
4 # Column work In Progress
5 - Lower ground 2 to Lower ground 1 Completed
6 - Lower ground 1 to Ground floor Completed
7 - Ground floor to First floor Completed
8 - First floor to Second floor Completed
9 - Second floor to Third floor Completed
10 - Third floor to 4th floor Completed
11 - 4th floor to 5th floor Completed
12 - 5th floor to 6th floor Completed
13 - 6th floor to 7th floor Completed
14 - 7th floor to 8th floor Completed
15 Sump tank Completed
16 Lift pit work Completed
17 # Ramp concrete In Progress
18 - Lower ground 2 to Lower ground 1 Completed
19 - Lower ground 1 to Ground floor Completed
20 # Slab work In Progress
21 - Lower ground 1 floor slab Completed
22 - Ground floor slab Completed
23 - First floor slab Completed
24 - Second floor slab Completed
25 - Third floor slab Completed
26 - 4th Floor slab Completed
27 - 5th Floor slab Completed
28 - 6th Floor slab Completed
29 - 7th Floor slab Completed
30 # Ceiling Plastering In Progress
31 - First floor Completed
32 - Second floor Completed
33 - Third floor Completed
34 - 4th Floor Completed
35 # Block work In Progress
36 - First floor Completed
37 - Second floor In Progress
38 - Third floor Completed
39 # Inside Plastering In Progress
40 - 1st floor In Progress
41 # Electrical work In Progress
42 - 1st floor Wall chasing and box fixing Completed
43 - 2nd floor Wall chasing and box fixing In Progress
Work status as of June 2026
Sl.No Work description Status
1 Retaining wall works Completed
2 Piling work Completed
3 Foundation including Pile cap, Grade beam and Grade slab work Completed
4 # Column work In Progress
5 - Lower ground 2 to Lower ground 1 Completed
6 - Lower ground 1 to Ground floor Completed
7 - Ground floor to First floor Completed
8 - First floor to Second floor Completed
9 - Second floor to Third floor Completed
10 - Third floor to 4th floor Completed
11 - 4th floor to 5th floor Completed
12 - 5th floor to 6th floor Completed
13 Sump tank Completed
14 Lift pit work Completed
15 # Ramp concrete In Progress
16 - Lower ground 2 to Lower ground 1 Completed
17 - Lower ground 1 to Ground floor Completed
18 # Slab work In Progress
19 - Lower ground 1 floor slab Completed
20 - Ground floor slab Completed
21 - First floor slab Completed
22 - Second floor slab Completed
23 - Third floor slab Completed
24 - 4th Floor slab Completed
25 - 5th Floor slab Completed
26 # Ceiling Plastering In Progress
27 - First floor Completed
28 - Second floor Completed
29 # Block work In Progress
30 - First floor Completed