Cordial Leora Work Status

Explore the work status of Cordial Leora, Super luxury Apartments in Trivandrum

Book a site visit
Work Status as of June, 2025
Retaining wall worksIn Progress
Piling workCompleted
Pile cap work60% Completed
Grade beam work50% Completed
Grade slab work30% Completed
Sump tankCompleted
Lift pit workCompleted
Work Status as of April 29, 2025
  • Retaining wall works : In progress
  • Piling work: Completed
  • Pie Cap work: 40% Completed
  • Grade Beam Work: 10% Completed
  • Sump Tank: 80% Completed
  • Lift Pit Work: 40% Completed
Work Status as of April 12, 2025
  • Piling completed in quick time of under 90 days along with successful Static load test on working pile.
  • Retaining wall completed for boundary.
  • Pile cap started with sump tank.
Work Status as of March 31, 2025
  • Retaining wall works : In Progress
  • Piling work: 75% Completed
  • Pile Cap Work: Started
March 2025
𝐒𝐭𝐚𝐭𝐢𝐜 𝐏𝐢𝐥𝐞 𝐋𝐨𝐚𝐝 𝐓𝐞𝐬𝐭 𝐒𝐮𝐜𝐜𝐞𝐬𝐬𝐟𝐮𝐥𝐥𝐲 𝐂𝐨𝐧𝐝𝐮𝐜𝐭𝐞𝐝 𝐚𝐭 𝐂𝐨𝐫𝐝𝐢𝐚𝐥 𝐋𝐞𝐨𝐫𝐚!
Ensuring strength, stability, and durability! The Static Pile Load Test has been successfully conducted at Cordial Leora, our newly launched super luxury apartment project at Kuravankonam, Trivandrum. This crucial test guarantees that the foundation meets the highest structural standards, reinforcing our commitment to excellence in construction.

Work status- Cordial Leora