| Sl. No | Work Description | Status |
|---|---|---|
| 1 | Retaining wall works | Completed |
| 2 | Piling work | Completed |
| 3 | Foundation incl. pile cap, grade beam & grade slab | Completed |
| 4 | Column Work | |
| Lower Ground 2 to Lower Ground 1 | Completed | |
| Lower Ground 1 to Ground Floor | Completed | |
| Ground Floor to First Floor | Completed | |
| First Floor to Second Floor | Completed | |
| Second Floor to Third Floor | Completed | |
| Third Floor to 4th Floor | Completed | |
| 4th Floor to 5th Floor | Completed | |
| 5th Floor to 6th Floor | Completed | |
| 6th Floor to 7th Floor | 50% Completed | |
| 5 | Sump tank | Completed |
| 6 | Lift pit work | Completed |
| 7 | Ramp Concrete | |
| Lower Ground 2 to Lower Ground 1 | Completed | |
| Lower Ground 1 to Ground Floor | Completed | |
| 8 | Slab Work | |
| Lower Ground 1 floor slab | Completed | |
| Ground floor slab | Completed | |
| First floor slab | Completed | |
| Second floor slab | Completed | |
| Third floor slab | Completed | |
| 4th floor slab | Completed | |
| 5th floor slab | Completed | |
| 6th floor slab | Completed | |
| 9 | Ceiling Plastering | |
| First floor | Completed | |
| Second floor | Completed | |
| Third floor | Completed | |
| 10 | Block Work | |
| First floor | Completed | |
| Second floor | In Progress | |
| Third floor | In Progress |
| Sl. No. | Work Description | Status |
|---|---|---|
| 1 | Retaining Wall Works | Completed |
| 2 | Piling Work | Completed |
| 3 | Foundation Including Pile Cap, Grade Beam & Grade Slab Work | Completed |
| 4 | Column Work | |
| 4.1 | Lower Ground 2 to Lower Ground 1 | Completed |
| 4.2 | Lower Ground 1 to Ground Floor | Completed |
| 4.3 | Ground Floor to First Floor | Completed |
| 4.4 | First Floor to Second Floor | Completed |
| 4.5 | Second Floor to Third Floor | Completed |
| 4.6 | Third Floor to Fourth Floor | Completed |
| 4.7 | Fourth Floor to Fifth Floor | Completed |
| 4.8 | Fifth Floor to Sixth Floor | 70% Completed |
| 5 | Sump Tank | Completed |
| 6 | Lift Pit Work | Completed |
| 7 | Ramp Concrete | |
| 7.1 | Lower Ground 2 to Lower Ground 1 | Completed |
| 7.2 | Lower Ground 1 to Ground Floor | Completed |
| 8 | Slab Work | |
| 8.1 | Lower Ground 1 Floor Slab | Completed |
| 8.2 | Ground Floor Slab | Completed |
| 8.3 | First Floor Slab | Completed |
| 8.4 | Second Floor Slab | Completed |
| 8.5 | Third Floor Slab | Completed |
| 8.6 | Fourth Floor Slab | Completed |
| 8.7 | Fifth Floor Slab | Completed |
| 9 | Ceiling Plastering | |
| 9.1 | First Floor | Completed |
| 9.2 | Second Floor | 25% Completed |
| 10 | Block Work | |
| 10.1 | First Floor | 50% Completed |
1 | Retaining wall works | Completed |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
| First floor to Second floor | Completed |
| Second floor to third floor | Completed |
| Third floor to 4th floor | Completed |
| 4th floor to 5th floor | Completed |
| 5th floor to 6th floor | In Progress |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | Completed |
| Second floor slab | Completed |
| Third floor slab | Completed |
| 4th Floor slab | Completed |
| 5th Floor slab | 75% Completed |
9 | Ceiling Plastering |
|
| First floor | In Progress |
Sl.No | Work Description | Status as on Mar.30, 2026 |
1 | Retaining wall works | Completed |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
| First floor to Second floor | Completed |
| Second floor to third floor | Completed |
| Third floor to 4th floor | Completed |
| 4th floor to 5th floor | In Progress |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | Completed |
| Second floor slab | Completed |
| Third floor slab | Completed |
| 4th Floor slab | Completed |
| 5th Floor slab | In Progress |
9 | Ceiling Plastering |
|
| First floor | In Progress |
1 | Retaining wall works | Completed |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
| First floor to Second floor | Completed |
| Second floor to third floor | Completed |
| Third floor to 4th floor | In Progress |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | Completed |
| Second floor slab | Completed |
| Third floor slab | Completed |
| 4th Floor slab | In Progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
| First floor to Second floor | Completed |
| Second floor to third floor | In Progress |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | Completed |
| Second floor slab | Completed |
| Third floor slab | In Progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
| First floor to Second floor | In Progress |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | Completed |
| Second floor slab | In Progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
| Ground floor to First floor | Completed |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | Completed |
8 | slab work |
|
| Lower ground 1 floor slab | Completed |
| Ground floor slab | Completed |
| First floor slab | In Progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | 100% Completed |
| Ground floor to First floor | 40% Completed |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | In progress |
8 | slab work |
|
| Lower ground 1 floor slab | 100% Completed |
| Ground floor slab | 75% Completed |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | 90% Completed |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | In progress |
8 | slab work |
|
| Lower ground 1 floor slab | 90% Completed |
| Ground floor slab | In progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 98% Completed |
4 | Grade beam work | 90% Completed |
5 | Grade slab work | 80% Completed |
6 | Column work |
|
| Lower ground 2 to Lower ground 1 | 90% Completed |
| Lower ground 1 to Ground floor | 50% Completed |
7 | Sump tank | Completed |
8 | Lift pit work | Completed |
9 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | In progress |
10 | slab work |
|
| Lower ground 1 floor | 80% Completed |
| Ground floor slab | In progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 85% Completed |
4 | Grade beam work | 75% Completed |
5 | Grade slab work | 70% Completed |
6 | Lower ground 2 to Lower ground 1 Column work | 75% Completed |
6 | Sump tank | Completed |
8 | Lift pit work | Completed |
9 | Ramp concrete (Lower ground 2 to Lower ground 1) | Completed |
10 | Lower ground 1 floor slab work | 50% Completed |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 80% Completed |
4 | Grade beam work | 70% Completed |
5 | Grade slab work | 50% Completed |
6 | Sump tank | Completed |
7 | Lift pit work | Completed |
8 | Ramp concrete (Lower ground 2 to Lower ground 1) | 80% Completed |
9 | Lower ground 1 slab work | In progress |