1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Foundation including Pile cap, Grade beam and Grade slab work | Completed |
4 | Column work |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | 90% Completed |
5 | Sump tank | Completed |
6 | Lift pit work | Completed |
7 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | In progress |
8 | slab work |
|
| Lower ground 1 floor slab | 90% Completed |
| Ground floor slab | In progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 98% Completed |
4 | Grade beam work | 90% Completed |
5 | Grade slab work | 80% Completed |
6 | Column work |
|
| Lower ground 2 to Lower ground 1 | 90% Completed |
| Lower ground 1 to Ground floor | 50% Completed |
7 | Sump tank | Completed |
8 | Lift pit work | Completed |
9 | Ramp concrete |
|
| Lower ground 2 to Lower ground 1 | Completed |
| Lower ground 1 to Ground floor | In progress |
10 | slab work |
|
| Lower ground 1 floor | 80% Completed |
| Ground floor slab | In progress |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 85% Completed |
4 | Grade beam work | 75% Completed |
5 | Grade slab work | 70% Completed |
6 | Lower ground 2 to Lower ground 1 Column work | 75% Completed |
6 | Sump tank | Completed |
8 | Lift pit work | Completed |
9 | Ramp concrete (Lower ground 2 to Lower ground 1) | Completed |
10 | Lower ground 1 floor slab work | 50% Completed |
1 | Retaining wall works | In Progress |
2 | Piling work | Completed |
3 | Pile cap work | 80% Completed |
4 | Grade beam work | 70% Completed |
5 | Grade slab work | 50% Completed |
6 | Sump tank | Completed |
7 | Lift pit work | Completed |
8 | Ramp concrete (Lower ground 2 to Lower ground 1) | 80% Completed |
9 | Lower ground 1 slab work | In progress |