1.Common area
- Land development works- 100% Completed
- Electrical works – 95% Completed
- Plumbing works – 100% Completed
- Interlock laying in common area – 80% Completed
- Recreation area landscaping – 100% Completed
- AC Multipurpose hall – 100% completed
- AC Health Club- 100% completed
- Outdoor children’s play area- 100% completed
2.Plot 1 – 85% Completed
3.Plot 2 – Completed & OC Obtained
4.Plot 3 – Completed & OC Obtained
5.Plot 4 – Completed & OC Obtained
6.Plot 5 – 70% Completed
7.Plot 6 – Completed & OC Obtained
8.Plot 7 – 70 % Completed
9.Plot 8 – Completed & OC Obtained
- Plot 9 – 25% Completed
- Plot 10 – 15% Completed
12.Plot 11 – Completed & OC Obtained
13.Plot 12 – Completed & OC Obtained
14.Plot 13 – 50% Completed
15.Plot 14 – Completed & OC Obtained