Cordial Rise-Work status

As of February 2024
Retaining wall works Completed
Project Structure Work Completed
Sewage Treatment Plant RCC works Completed
Ceiling Plastering Completed
Internal Plastering Up to Sixth floor Completed
Electrical work In Progress
External Plastering In Progress
Plumbing work In Progress
Water proofing work In Progress
Painting work In Progress
Fabrication work- Balcony handrail, window grill In Progress
Flooring and Tiling In Progress
As of October 2023
Retaining wall works Completed
Project Structure Work Completed
Sewage Treatment Plant RCC works Completed
Ceiling Plastering Completed
Internal Plastering Up to Sixth floor Completed
Electrical work In Progress
External Plastering In Progress
Plumbing work In Progress
Water proofing work In Progress
Painting work In Progress
Fabrication work- Balcony handrail, window grill In Progress
Flooring and Tiling In Progress
Cordial Rise- August 2023
Retaining wall works Completed
Project Structure Work Completed
Sewage Treatment Plant RCC works Completed
Ceiling Plastering Completed
Masonry work – Up to Seventh floor Completed
Electrical work – Up to Seventh floor Completed
Internal Plastering Up to Sixth floor Completed
External Plastering In Progress
Plumbing work In Progress
Water proofing work In Progress
Painting work In Progress
Fabrication work- Balcony handrail, window grill In Progress
Cordial Rise as of June 24, 2023
  • Retaining wall works: 100%
  • Foundation connected works: 100%
  • Sewage Treatment Plant RCC works: Completed
  • Basement 3 structural works: Completed
  • Basement 2 floor slab: Completed
  • Basement 1 floor slab: Completed
  • Ground floor slab: Completed
  • First floor slab: Completed
  • Second floor slab: Completed
  • Third floor Slab: Completed
  • Fourth floor Slab: Completed
  • Fifth floor slab: Completed
  • Sixth floor slab: Completed
  • Seventh floor slab: Completed
  • Eighth floor slab: Completed
  • Roof slab concrete work: Completed
  • Staircase headroom works: In Progress
  • Ceiling Plastering : 7th floor In Progress
  • Masonry work – Second floor Completed
  • Masonry work – First floor Completed
  • Masonry work – Third floor Completed
  • Masonry work – Fourth floor Completed
  • Masonry work – Fifth floor Completed
  • Masonry work – Sixth floor Completed
  • Masonry work – Seventh floor In Progress
  • Electrical work – Second floor – Wall chasing & box fixing Completed
  • Electrical work – First floor – Wall chasing & box fixing Completed
  • Electrical work – Third floor – Wall chasing & box fixing Completed
  • Electrical work – Fourth floor – Wall chasing & box fixing Completed
  • Electrical work – Fifth floor – Wall chasing & box fixing In Progress
  • Internal Plastering – Second floor Completed
  • Internal Plastering – First floor Completed
  • Internal Plastering – Third floor Completed
  • Internal Plastering – Fourth floor In Progress
  • Plumbing work- Second floor In Progress
Cordial Rise-May 2023
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • 1st floor slab -Completed
  • 2nd floor slab -Completed
  • 3rd floor slab -Completed
  • 4th floor slab -Completed
  • 5th floor slab -Completed
  • 6th Floor Slab – Completed
  • 7th Floor Slab – Completed
  • 8th Floor Slab – Completed
  • Roof Slab – Work in Progress
  • Block Work – 6th floor in progress
  • Plastering – 3rd floor in progress
  • Eletrical Work – 3rd floor in progress
As of February 2023
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • 1st floor slab -Completed
  • 2nd floor slab -Completed
  • 3rd floor slab -Completed
  • 4th floor slab -Completed
  • 5th floor slab -Completed
  • 6th Floor Slab – Completed
  • 7th Floor Slab – Work in Progress
  • Block Work – Commenced
  • Plastering – Commenced
Rise-As of December 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • 1st floor slab -Completed
  • 2nd floor slab -Completed
  • 3rd floor slab -Completed
  • 4th floor slab -Completed
  • 5th floor slab -Completed
  • 6th Floor Slab – Work in Progress
  • Plastering – Commenced
October 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • First floor slab -Completed
  • 2nd floor Slab – Completed
September 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • First floor slab -Completed
  • Column concreting –First floor 65%
August 2022
  • Foundation – 100% Completed
  • Retain wall – 100% Completed
  • STP Structure – 100% Completed
  • Basement 3 – 100% Completed
  • Basement 2 – 100% Completed
  • Basement 1 – 100% Completed
  • Ground Floor – 100% Completed
  • First Floor – 30% Completed
Status as of 15 July 2022
  • Retaining wall works: 100% completed
  • Foundation connected works: 100% completed
  • Sewage Treatment Plant RCC works: Completed
  • Basement 3 structural works: Completed
  • Basement 2 floor slab: Completed
  • Basement 1 floor slab: Completed
  • Ground floor slab: Completed
  • Column concreting –Ground floor: In Progress