Cordial Rise-Work status
- Foundation & Development Works – Completed
- Sewage Treatment Plant RCC works -Completed
- Basement 3 structural works -Completed
- Basement 2 floor slab -Completed
- Basement 1 floor slab -Completed
- Ground floor slab -Completed
- 1st floor slab -Completed
- 2nd floor slab -Completed
- 3rd floor slab -Completed
- 4th floor slab -Completed
- 5th floor slab -Completed
- 6th Floor Slab – Work in Progress
- Plastering – Commenced
- Retaining wall works: 100% completed
- Foundation connected works: 100% completed
- Sewage Treatment Plant RCC works: Completed
- Basement 3 structural works: Completed
- Basement 2 floor slab: Completed
- Basement 1 floor slab: Completed
- Ground floor slab: Completed
- Column concreting –Ground floor: In Progress