Cordial Rise-Work status

Rise-As of December 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • 1st floor slab -Completed
  • 2nd floor slab -Completed
  • 3rd floor slab -Completed
  • 4th floor slab -Completed
  • 5th floor slab -Completed
  • 6th Floor Slab – Work in Progress
  • Plastering – Commenced
October 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • First floor slab -Completed
  • 2nd floor Slab – Completed
September 2022
  • Foundation & Development Works – Completed
  • Sewage Treatment Plant RCC works -Completed
  • Basement 3 structural works -Completed
  • Basement 2 floor slab -Completed
  • Basement 1 floor slab -Completed
  • Ground floor slab -Completed
  • First floor slab -Completed
  • Column concreting –First floor 65%
August 2022
  • Foundation – 100% Completed
  • Retain wall – 100% Completed
  • STP Structure – 100% Completed
  • Basement 3 – 100% Completed
  • Basement 2 – 100% Completed
  • Basement 1 – 100% Completed
  • Ground Floor – 100% Completed
  • First Floor – 30% Completed
Status as of 15 July 2022
  • Retaining wall works: 100% completed
  • Foundation connected works: 100% completed
  • Sewage Treatment Plant RCC works: Completed
  • Basement 3 structural works: Completed
  • Basement 2 floor slab: Completed
  • Basement 1 floor slab: Completed
  • Ground floor slab: Completed
  • Column concreting –Ground floor: In Progress