Cordial Rise-Work status
Retaining wall works | Completed |
Project Structure Work | Completed |
Sewage Treatment Plant RCC works | Completed |
Ceiling Plastering | Completed |
Internal Plastering Up to Sixth floor | Completed |
Electrical work | In Progress |
External Plastering | In Progress |
Plumbing work | In Progress |
Water proofing work | In Progress |
Painting work | In Progress |
Fabrication work- Balcony handrail, window grill | In Progress |
Flooring and Tiling | In Progress |
Retaining wall works | Completed |
Project Structure Work | Completed |
Sewage Treatment Plant RCC works | Completed |
Ceiling Plastering | Completed |
Internal Plastering Up to Sixth floor | Completed |
Electrical work | In Progress |
External Plastering | In Progress |
Plumbing work | In Progress |
Water proofing work | In Progress |
Painting work | In Progress |
Fabrication work- Balcony handrail, window grill | In Progress |
Flooring and Tiling | In Progress |
Retaining wall works | Completed |
Project Structure Work | Completed |
Sewage Treatment Plant RCC works | Completed |
Ceiling Plastering | Completed |
Internal Plastering Up to Sixth floor | Completed |
Electrical work | In Progress |
External Plastering | In Progress |
Plumbing work | In Progress |
Water proofing work | In Progress |
Painting work | In Progress |
Fabrication work- Balcony handrail, window grill | In Progress |
Flooring and Tiling | In Progress |
Retaining wall works | Completed |
Project Structure Work | Completed |
Sewage Treatment Plant RCC works | Completed |
Ceiling Plastering | Completed |
Masonry work – Up to Seventh floor | Completed |
Electrical work – Up to Seventh floor | Completed |
Internal Plastering Up to Sixth floor | Completed |
External Plastering | In Progress |
Plumbing work | In Progress |
Water proofing work | In Progress |
Painting work | In Progress |
Fabrication work- Balcony handrail, window grill | In Progress |
- Retaining wall works: 100%
- Foundation connected works: 100%
- Sewage Treatment Plant RCC works: Completed
- Basement 3 structural works: Completed
- Basement 2 floor slab: Completed
- Basement 1 floor slab: Completed
- Ground floor slab: Completed
- First floor slab: Completed
- Second floor slab: Completed
- Third floor Slab: Completed
- Fourth floor Slab: Completed
- Fifth floor slab: Completed
- Sixth floor slab: Completed
- Seventh floor slab: Completed
- Eighth floor slab: Completed
- Roof slab concrete work: Completed
- Staircase headroom works: In Progress
- Ceiling Plastering : 7th floor In Progress
- Masonry work – Second floor Completed
- Masonry work – First floor Completed
- Masonry work – Third floor Completed
- Masonry work – Fourth floor Completed
- Masonry work – Fifth floor Completed
- Masonry work – Sixth floor Completed
- Masonry work – Seventh floor In Progress
- Electrical work – Second floor – Wall chasing & box fixing Completed
- Electrical work – First floor – Wall chasing & box fixing Completed
- Electrical work – Third floor – Wall chasing & box fixing Completed
- Electrical work – Fourth floor – Wall chasing & box fixing Completed
- Electrical work – Fifth floor – Wall chasing & box fixing In Progress
- Internal Plastering – Second floor Completed
- Internal Plastering – First floor Completed
- Internal Plastering – Third floor Completed
- Internal Plastering – Fourth floor In Progress
- Plumbing work- Second floor In Progress
- Foundation & Development Works – Completed
- Sewage Treatment Plant RCC works -Completed
- Basement 3 structural works -Completed
- Basement 2 floor slab -Completed
- Basement 1 floor slab -Completed
- Ground floor slab -Completed
- 1st floor slab -Completed
- 2nd floor slab -Completed
- 3rd floor slab -Completed
- 4th floor slab -Completed
- 5th floor slab -Completed
- 6th Floor Slab – Completed
- 7th Floor Slab – Completed
- 8th Floor Slab – Completed
- Roof Slab – Work in Progress
- Block Work – 6th floor in progress
- Plastering – 3rd floor in progress
- Eletrical Work – 3rd floor in progress
- Foundation & Development Works – Completed
- Sewage Treatment Plant RCC works -Completed
- Basement 3 structural works -Completed
- Basement 2 floor slab -Completed
- Basement 1 floor slab -Completed
- Ground floor slab -Completed
- 1st floor slab -Completed
- 2nd floor slab -Completed
- 3rd floor slab -Completed
- 4th floor slab -Completed
- 5th floor slab -Completed
- 6th Floor Slab – Completed
- 7th Floor Slab – Work in Progress
- Block Work – Commenced
- Plastering – Commenced
- Foundation & Development Works – Completed
- Sewage Treatment Plant RCC works -Completed
- Basement 3 structural works -Completed
- Basement 2 floor slab -Completed
- Basement 1 floor slab -Completed
- Ground floor slab -Completed
- 1st floor slab -Completed
- 2nd floor slab -Completed
- 3rd floor slab -Completed
- 4th floor slab -Completed
- 5th floor slab -Completed
- 6th Floor Slab – Work in Progress
- Plastering – Commenced
- Retaining wall works: 100% completed
- Foundation connected works: 100% completed
- Sewage Treatment Plant RCC works: Completed
- Basement 3 structural works: Completed
- Basement 2 floor slab: Completed
- Basement 1 floor slab: Completed
- Ground floor slab: Completed
- Column concreting –Ground floor: In Progress