Cordial I-Nest-Work status
- Common area
Land development works- 100% Completed
Electrical works – 75% Completed
Plumbing works – 85% Completed
Interlock laying in common area – 80% Completed
Recreation area landscaping – 60% Completed - Plot 1 – 75% Completed
- Plot 2 – Completed & OC Obtained
- Plot 3 – Completed & OC Obtained
- Plot 4 – Completed & OC Obtained
- Plot 5 – 50% Completed
- Plot 6 – Completed & OC Obtained
- Plot 7 – 40 % Completed
- Plot 8 – Completed & OC Obtained
- Plot 9 – 15% Completed
- Plot 10 – 5% Completed
- Plot 11 – Completed & OC Obtained
- Plot 12 – 90% Completed
- Plot 13 – 35% Completed
- Plot 14 – Completed & OC Obtained
As of May 20, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress
As of April 20, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress
As of March 31, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress