Cordial I-Nest-Work status
1.Common area
- Land development works- 100% Completed
- Electrical works – 95% Completed
- Plumbing works – 100% Completed
- Interlock laying in common area – 80% Completed
- Recreation area landscaping – 100% Completed
- AC Multipurpose hall – 100% completed
- AC Health Club- 100% completed
- Outdoor children’s play area- 100% completed
2.Plot 1 – 85% Completed
3.Plot 2 – Completed & OC Obtained
4.Plot 3 – Completed & OC Obtained
5.Plot 4 – Completed & OC Obtained
6.Plot 5 – 70% Completed
7.Plot 6 – Completed & OC Obtained
8.Plot 7 – 70 % Completed
9.Plot 8 – Completed & OC Obtained
- Plot 9 – 25% Completed
- Plot 10 – 15% Completed
12.Plot 11 – Completed & OC Obtained
13.Plot 12 – Completed & OC Obtained
14.Plot 13 – 50% Completed
15.Plot 14 – Completed & OC Obtained
- Villa 1- 80% completed
- Villa 2- Completed and OC Obtained
- Villa 3- Completed and OC Obtained
- Villa 4- Completed and OC Obtained
- Villa 5- 70% completed
- Villa 6- Completed and OC Obtained
- Villa 7- 70% completed
- Villa 8- Completed and OC Obtained
- Villa 9- Ground Floor Block work in progress
- Villa 10- Footing and Foundation works completed
- Villa 11- Completed and OC Obtained
- Villa 12- Completed and OC Obtained
- Villa 13- Internal and External plastering in progress
- Recreation Block- Completed and OC Obtained
- Roads and Landscape works- Completed
- Badminton court and Children’s play area- Works in Progress
- Common area
Land development works- 100% Completed
Electrical works – 75% Completed
Plumbing works – 85% Completed
Interlock laying in common area – 80% Completed
Recreation area landscaping – 60% Completed - Plot 1 – 75% Completed
- Plot 2 – Completed & OC Obtained
- Plot 3 – Completed & OC Obtained
- Plot 4 – Completed & OC Obtained
- Plot 5 – 50% Completed
- Plot 6 – Completed & OC Obtained
- Plot 7 – 40 % Completed
- Plot 8 – Completed & OC Obtained
- Plot 9 – 15% Completed
- Plot 10 – 5% Completed
- Plot 11 – Completed & OC Obtained
- Plot 12 – 90% Completed
- Plot 13 – 35% Completed
- Plot 14 – Completed & OC Obtained
As of May 20, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress
As of April 20, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress
As of March 31, 2025, all villas at Cordial I-Nest are in the finishing stage, with several already handed over to proud owners.
- Land Development Works – Completed
- Plot Division – Completed
- Retaining Walls – Completed
- Club House Structure – Completed
- Club House Plastering – Completed
- Individual villas – Work in progress
- Club House plumbing and electrical – work in progress